Construction Adjudication in Ontario in 2026: A Guide for Small Contractors

Types of Construction Liens

Your invoice is overdue and the other party says they’re withholding payment over an extra you billed. Before you spend more time chasing the invoice, check whether the dispute qualifies for construction adjudication and whether you have a separate lien deadline to meet.

Quick Answer

Construction adjudication is a process under Ontario’s Construction Act that lets an independent adjudicator decide eligible construction disputes, including disputes over payment. The adjudicator generally has 30 days from receipt of the claimant’s required documents to make a decision, subject to an extension. The decision binds the parties on an interim basis, and an amount ordered payable is generally due within 15 days after the decision is communicated. Check lien deadlines separately because adjudication can affect lien expiry in specific circumstances.

What disputes can construction adjudication cover?

Common examples include a disagreement about the value of work performed, payment under a contract or subcontract, and amounts withheld. The 2026 framework can also cover certain disputes about scope, requests to change the contract price, and requests for more time. Check the contract, the applicable rules and the issue you want decided before starting. AG Law’s overview of the Ontario Construction Act changes in 2026 puts adjudication in the broader context of invoicing, holdbacks and liens.

How prompt payment and construction adjudication work together

Prompt payment sets deadlines for paying or disputing a proper invoice. A proper invoice is a contractor’s written request for payment that meets the Act’s requirements, subject to its rules for when an invoice is deemed proper. At the owner-to-contractor level, an owner generally has 14 days after receiving a proper invoice to deliver a notice of non-payment for an amount they dispute. Payment of the undisputed amount is generally due within 28 days of receipt. Payments and notices further down the subcontracting chain follow separate rules.

Adjudication provides a way to get an interim decision on an eligible dispute. If you’re a subcontractor, keep any notice you receive and record the date. For some notices based on an owner’s non-payment, the contractor must undertake to refer the matter to adjudication within 21 days after giving the notice to the subcontractor. The type of notice matters.

What are the timelines for adjudication under the Construction Act?

The clock for starting adjudication and the clock for getting a decision run from different events. Under the current Ontario Construction Act, the notice deadline also depends on whether your dispute is under a contract or a subcontract. Transition rules can affect which version of the law applies.

Step General timing under the 2026 rules
Start a contract adjudication Give notice within 90 days after the contract is completed, abandoned or terminated, unless the parties agree otherwise.
Start a subcontract adjudication Give notice within 90 days of the earliest applicable event: completion, abandonment or termination of the prime contract, certification of the subcontract under section 33, or the subcontractor’s last supply under the subcontract. The parties can agree otherwise.
Submit supporting documents Generally within five days after the adjudicator agrees or is appointed to act.
Receive a determination Generally within 30 days after the adjudicator receives the required documents. The deadline can be extended under the Act.
Pay an amount ordered Within 15 days after the determination is communicated to the parties, subject to statutory holdback requirements.

The ODACC adjudication process guide explains how parties submit a notice, select an adjudicator and exchange documents. Prepare your supporting records before giving notice so you can meet the short submission window. 

Construction dispute adjudication vs. court in Ontario

The choice depends on what you need decided, how quickly you need a decision, and whether property security matters. A narrow payment dispute supported by a signed scope, approved extras and delivery records is easier to present on an accelerated schedule than a dispute involving several trades, conflicting expert opinions and competing delay claims. 

Route What it does What to weigh
Adjudication Gives an interim binding decision on an eligible dispute. Short filing and evidence windows, adjudicator fees and the possibility of later proceedings.
Court action Can finally determine legal rights and remedies in the action. The time and cost of litigation, especially where witnesses, expert evidence or several parties are involved.
Construction lien Can secure an eligible claim against an interest in the improved property. Separate steps to preserve and perfect the lien, each with its own deadline.

Pros and cons of adjudication for small contractors

The main benefit is speed when a disputed invoice is straining cash flow. A focused determination can establish what must be paid while the parties work out the rest of the dispute. The trade-off is that you need to assemble the evidence quickly, budget for adjudication fees and consider the cost of enforcing the determination if the other party still fails to pay. A certified determination can be filed with the court and enforced as a court order. 

What is the relationship between liens and adjudication?

A lien protects a potential source of payment through a claim tied to the improved property. Adjudication decides an eligible dispute between the parties. The same unpaid work can raise both issues, so identify both sets of deadlines early. The Act contains a lien-expiry rule that can apply when the matter that would be the subject of the lien is referred to adjudication while the lien is still alive. Have the dates and the scope of the referral checked before relying on that rule.

The type of work matters as well. If your invoice is for drawings or specifications on a project that never started, see AG Law’s guide to lien rights for design professionals in Ontario.

construction adjudication

What should you gather before giving notice?

Build a short timeline from the contract and invoice through to the latest payment response. Next to each disputed amount, identify the document that shows what was agreed, what you supplied and how you calculated the balance.

  • Signed contract or subcontract, scope and payment terms
  • Change orders and written approvals for extras
  • Invoices and proof of when they were sent and received
  • Notices of non-payment and explanations for any deduction
  • Site records, delivery slips, photos and payment history
  • Dates of last supply, certification, completion, termination or abandonment, where applicable

For example, if the other party approved an extra by email and later deducted it from your invoice, put the approval, proof of completion and deduction notice together. That gives the adjudicator a direct way to follow the disputed amount.

Discuss your unpaid construction invoice with AG Law

If an invoice is overdue or you’ve received a notice of non-payment, bring your contract, invoice, payment notices and key dates to a consultation with AG Law’s construction lien lawyers. Ask which deadlines apply to your project and how a potential lien fits with your payment dispute.

FAQs

Possibly. Under the 2026 rules, adjudication may be available after work ends. For a subcontractor, the last supply date can trigger the 90-day window even if the overall project is still underway. Check the applicable rules and the earliest relevant date.

 

An eligible dispute can generally be referred to adjudication even if it is already in court or arbitration, provided it has yet to be finally determined. Check how the referral would interact with the existing proceeding and any lien steps.

The parties generally split the adjudicator’s fee equally. Each party generally bears its own other costs, although the Act allows the adjudicator to order costs in certain circumstances involving party conduct.

The determination binds the parties until the matter is decided by a court or arbitration, or the parties resolve it in writing. The Act also allows judicial review with the court’s permission on limited grounds.

Do not rely on issuing or reissuing an invoice to extend a statutory deadline. A lawyer should identify the applicable trigger from the services, contract and project history.